AngloGold Ashanti has interests in three gold mining operations, all of which it manages in Mali. They are Sadiola, Yatela and Morila. The Malian operations together produced 441,000 attributable ounces of gold in 2007, equivalent to 8% of group production.
Ownership of these three operations is as follows:
Description: Sadiola is situated in the far south-west of the country, 77 kilometres to the south of the regional capital of Kayes. Mining takes place in five open pits and the ore mined is treated and processed in a 435,000Mtpm (5.2Mtpa) CIP gold plant.
Safety: Overall safety standards were maintained at Sadiola with an LTIFR for the year of 1.11 (2006: 1.02). No fatalities were recorded.
Operating review: Attributable production at Sadiola declined year-on-year by 26% to 140,000 ounces (2006: 190,000 ounces). While there was a steady increase in production during the course of the year, this failed to make up for the sharp drop which had occurred during the first quarter of the year. This decline in the throughput of tonnes was a result of plant optimisation to improve recovery of sulphide ores. The decline in the grade of feed to the plant was a result of a decision to withhold high-grade sulphide feed prior to the commissioning of the gravity circuit at the concentrator in December 2007. Consequently, total cash costs rose sharply by 53% to $414/oz (2006: $270/oz).
Adjusted gross profit was also down as a result, declining by 51% on the year to $24 million (2006: $49 million), mainly as a result of the reduced level of gold sales.
Total capital expenditure of $16 million attributable $6 million was spent during the year. A new gravity circuit was installed at the metallurgical plant to improve the recovery rates for the sulphide ores.
Growth prospects: Various options are to be reviewed in the coming year to improve current assumptions in the Deep Sulphide Project concerning mining method, scale, energy, and metallurgical recovery in order to convert the vast indicated resource below the main pit into reserve. A significant improvement was made in the understanding of sulphide ore recovery in 2007 and the commissioning of the new gravity circuit at the concentrator towards the end of 2007 will enable recovery of the very high-grade sulphide ores on stockpile in 2008.
Outlook: Attributable production at Sadiola is projected to be between 155,000 and 160,000 ounces at a total cash cost of between $455/oz and $465/oz. Capital expenditure is planned to be $9 million ($3 million attributable).
| Sadiola | 2007 | 2006 | 2005 | ||
|---|---|---|---|---|---|
| Pay limit | (oz/t) | 0.08 | 0.06 | 0.05 | |
| (g/t) | 2.46 | 1.98 | 1.80 | ||
| Recovered grade | (oz/t) | 0.081 | 0.094 | 0.080 | |
| (g/t) | 2.76 | 3.22 | 2.73 | ||
| Gold production | (000oz) | 100% | 369 | 500 | 442 |
| 38% | 140 | 190 | 168 | ||
| Total cash costs | ($/oz) | 414 | 270 | 265 | |
| Total production costs | ($/oz) | 462 | 335 | 336 | |
| Adjusted gross profit | ($m) | 100% | 63 | 129 | 53 |
| 38% | 24 | 49 | 20 | ||
| Capital expenditure | ($m) | 100% | 16 | 11 | 18 |
| 38% | 6 | 4 | 7 | ||
| Total number of employees | 100% | 1,529 | 1,294 | 1,245 | |
| Employees | 618 | 589 | 584 | ||
| Contractors | 911 | 705 | 661 |
Description: Yatela is situated some 25 kilometres north of Sadiola and approximately 50 kilometres south-south-west of Kayes. This is a single pit operation. The ore mined is treated at a heap-leach pad together with carbon-loading. The carbon is then eluted and the gold smelted at nearby Sadiola.
Safety: Overall safety standards improved at Yatela with an LTIFR for the year of 0.39 (2006: 0.43). No fatalities were recorded.
Operating review: Attributable gold production at Yatela declined by 15% to 120,000 ounces (2006: 141,000 ounces). Mining from the bottom of the main pit was completed in July 2007, after which lower grade ore from the stockpiles was fed to the heap leach pad.
Total cash costs increased dramatically, to $322/oz as a result of the decline in gold production, the appreciation of the euro and the FCFA against the dollar, and higher fuel prices.
There was a decline in attributable adjusted gross profit to $30 million (2006: $44 million).
Capital expenditure of $5 million (attributable $2 million) increased in 2007 and was spent mostly on additional leach pads to accommodate the extension in the life of mine.
Growth prospects: The push back 7 project will allow the operation to access the bottom of the main pit in 2009.
Outlook: Attributable production at Yatela is projected to decrease to between 63,000 and 73,000 ounces. Total cash costs are expected to rise to between $518/oz and $528/oz as a result of the expected grade-related decline in gold production. Capital expenditure of $6 million ($3 million attributable) is planned to to be spent mostly on additional leach pads.
| Yatela | 2007 | 2006 | 2005 | ||
|---|---|---|---|---|---|
| Pay limit | (oz/t) | 0.04 | 0.06 | 0.05 | |
| (g/t) | 1.37 | 1.79 | 1.66 | ||
| Recovered grade | (oz/t) | 0.101 | 0.120 | 0.087 | |
| (g/t) | 3.46 | 4.12 | 2.99 | ||
| Gold production | (000oz) | 100% | 301 | 352 | 246 |
| 40% | 120 | 141 | 98 | ||
| Total cash costs | ($/oz) | 322 | 228 | 263 | |
| Total production costs | ($/oz) | 381 | 299 | 340 | |
| Adjusted gross profit | ($m) | 100% | 75 | 110 | 27 |
| 40% | 30 | 44 | 11 | ||
| Capital expenditure | ($m) | 100% | 5 | 3 | 5 |
| 40% | 2 | 1 | 2 | ||
| Total number of employees | 100% | 903 | 878 | 910 | |
| Employees | 265 | 203 | 210 | ||
| Contractors | 638 | 675 | 700 |
Description: The Morila mine is situated some 180 kilometres by road south-east of Bamako, the capital of Mali. Open-pit mining takes place at five cuts within one pit. The current focus is on cuts 4 and 5. At its peak, the Morila pit will be approximately 1.4 kilometres by 1 kilometres and up to 240 metres deep. The plant, which comprises a conventional carbon-in-leach (CIL) process with an upfront gravity section to extract the free gold, has throughput capacity of 350,000tpm and 4.2Mtpa.
Safety: Overall, the level of lost-time injuries was maintained at Morila with an LTIFR for the year of 0.57 per million man hours worked (2006: 1.42). The OHSAS 18001 Safety Management certification was achieved by November 2007. Sadly, the Morila team lost two fellow colleagues on 9 February during an explosion caused by the inadvertent mixing of two chemicals. This resulted in a FIFR for the year of 0.57 per million man hours (2006: 0).
Operating review: Attributable gold production at Morila decreased by 13% to 180,000 ounces (2006: 207,000 ounces), with the significant increase in production in the second half of the year not quite making up for the losses recorded in the first half of the year. The initial fall in production levels was a result of a decline in the recovered grade which improved markedly later in the year with the mining and processing of higher grade ore.
Mining production efficiencies improved significantly in the second half of 2007 as highlighted by the achievement of 1,001,444 BCMs in September month. The optimal use of in-pit backfill (leaving waste in the pit) resulted in significant savings and an increase in mining production.
Total cash costs increased by 27% to $350/oz largely owing to the decline in production and an increase in cash costs caused by higher fuel costs and a weakening in the dollar against the FCFA and the euro. As a result, fuel, local salaries, mining contractor and certain reagent costs increased significantly.
Adjusted gross profit for the year decreased by 27% to $38 million (2006: $52 million) primarily as a result of the decline in gold production and increased production costs. Capital expenditure of $1.3 million (attributable $0.5 million) in 2007.
Growth prospects: Good progress was made with the current drilling programme and broad zones of mineralisation have been identified along the eastern margin of the pit at a depth (565 metres). A follow-up drilling programme for this area will be proposed for 2008. A pitting programme in the Sokela area, situated 8 kilometres south-west of the main pit is progressing well. This programme will establish the feasibility of drilling in this area.
Outlook: In 2008, attributable production at Morila is projected to be between 182,000 and 187,000 ounces while total cash costs are forecast to increase to range between $361/oz and $371/oz. Capital expenditure of $4 million ($2 million attributable) is planned.
| Morila | 2007 | 2006 | 2005 | ||
|---|---|---|---|---|---|
| Pay limit | (oz/t) | 0.08 | 0.08 | 0.07 | |
| (g/t) | 2.46 | 2.41 | 2.27 | ||
| Recovered grade | (oz/t) | 0.098 | 0.113 | 0.158 | |
| (g/t) | 3.36 | 3.88 | 5.41 | ||
| Gold production | (000oz) | 100% | 450 | 517 | 655 |
| 40% | 180 | 207 | 262 | ||
| Total cash costs | ($/oz) | 350 | 275 | 191 | |
| Total production costs | ($/oz) | 421 | 349 | 293 | |
| Adjusted gross profit | ($m) | 100% | 95 | 130 | 96 |
| 40% | 38 | 52 | 39 | ||
| Capital expenditure | ($m) | 100% | 1.3 | 3 | 5 |
| 40% | 0.5 | 1 | 2 | ||
| Total number of employees | 100% | 1,686 | 1,575 | 1,183 | |
| Employees | 498 | 500 | 478 | ||
| Contractors | 1,188 | 1,075 | 705 |
AngloGold Ashanti Annual Report 2007 – Annual Financial Statements